View Case Filings for: 2015-00051


Case Number:2015-00051
Service Type:Electric
Filing Date:4/7/2015
Category:Regular
Utilities:

Big Rivers Electric Corporation



Case Nature:

APPLICATION OF BIG RIVERS ELECTRIC CORPORATION FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT TWO 161 KV TRANSMISSION LINES IN HANCOCK COUNTY, KENTUCKY









View Post Case Files
Case Filings
FilingDocuments
1/15/2016

Order Entered: 1. Movant's motion for confidential protection of its response to the Staff's Initial Request, Item 17, is granted. 2. Pursuant to KRS 61.878, the information for which Movant requests confidential protection shall not be placed in the public record or made available for public inspection for an indefinite period of time, or until further Order of the Commission. 3. Use of the materials in question in any Commission proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 4. Movant shall inform the Commission if the materials in question become publicly available or no longer qualify for confidential treatment. 5. If a non-party to this proceeding requests to inspect materials granted confidential treatment by this Order, the Movant shall have 20 days from receipt of written notice of the request to demonstrate that the materials still fall within the exclusions from disclosure requirements established in KRS 61.878. If Movant is unable to make such demonstration, the requested materials shall be made available for inspection.

PSC_ORDER

8/4/2015

Order Entered: Big Rivers is granted a CPCN to construct and operate the proposed transmission lines as set forth in its application. 2. Big Rivers shall file a survey of the final location of the line after any modifications are finalized as authorized herein and before construction begins. 3. Big Rivers shall file "as-built drawings or maps within 60 days of the completion of the construction authorized by this Order.

PSC_ORDER

7/31/2015

Letter from Andrew Ishmael, VP with Aleris International

Letter from Andrew Ishmael, VP with Aleris International

6/19/2015

Big Rivers Electric Corp. Response to Supplemental Request

Big Rivers Electric Corp. Response to Supplemental Request

6/17/2015

Letter Filing Visual Impact Evaluation into the Record

PSC_Letter Filing Visual Impact Evaluation into Record

6/8/2015

Commission Staff's Supplemental Request for Information to Big Rivers Electric Corporation

DATA_REQUEST

5/27/2015

Big Rivers Electric Corp. Notice of Publication

Big Rivers Electric Corp. Notice of Publication

5/27/2015

Big Rivers Electric Corp. Response to Request for Information

Big Rivers Electric Corp. Response to Request for Information

5/27/2015

Big Rivers Electric Corp. Motion for Confidential Treatment

Big Rivers Electric Corp. Motion for Confidential Treatment

5/15/2015

Commission Staff's Initial Request for Information to Big Rivers Electric Corporation

DATA_REQUEST

5/8/2015

Thomas K. Baird Contact Information

Thomas K. Baird Contact Information

5/1/2015

Order Entered: The time in which the Commission must issue its decision in this case is extended to 120 days. 2. The procedural schedule set forth in the Appendix attached to this Order shall be followed.

PSC_ORDER

4/27/2015

Order Entered: 1. The motion of Mr. Baird to intervene is granted. 2. Mr. Baird shall be entitled to the full rights of a party and shall be served with the Commission's Orders and with filed testimony, exhibits, pleadings, correspondence, and all other documents submitted by parties after the date of this Order. 3. Should Mr. Baird file documents of any kind with the Commission in the course of these proceedings, Mr. Baird shall also serve a copy of said documents on all other parties of record, in accordance with 607 KAR 5:001, Section 4(8)(d). 4. Within 15 days of entry of this Order, Mr. Baird shall provide his electronic mail address so documents issued by the Commission may be served upon him in accordance with 807 KAR 5:001, Section 4(8)(b).

PSC_ORDER

4/16/2015

No Deficiency Letter

PSC_No Deficiency Letter

4/13/2015

Thomas Baird Request to Intervene

Thomas Baird Request to Intervene

4/7/2015

Acknowledge Receipt of Filing

PSC_Acknowledgement Letter

4/7/2015

Big Rivers Electric Corporation Application for a Certificate of Public Convenience and Necessity to Construct Two 161 kV Transmission Lines in Hancock County, Kentucky

Big Rivers Electric Corporation_Application

2/12/2015

Acknowledge Receipt of Filing

PSC_Acknowledgement Letter

2/12/2015

Big Rivers Electric Corporation Notice of Intent to File Application for a CPC&N to Construct Two 161 kV Transmission Lines in Hancock County, KY

Big Rivers Electric Corporation_Notice of Intent